December 2020
RCC Slabs completed and Internal Finishing works in progress.
November 2020
Terrace Floor Completed.
October 2020
15th Floor slab at completion.
September 2020
13th Floor slab WIP
August 2020
12th Floor Slab WIP
July 2020
11th Floor Slab WIP
June 2020
9th floor slab WIP
May 2020
8th floor slab complete, work for 9th floor slab started.
April 2020
8th Floor slab WIP
March 2020
7th Floor slab at completion
February 2020
5th Floor slab WIP
January 2020
2nd Floor Slab WIP