December 2020
RCC Slabs completed and Internal Finishing works in progress.
November 2020
Terrace Floor Completed.
October 2020
17th Floor Slab at completion.
September 2020
15th Floor Slab at completion.
August 2020
14th Floor Slab WIP
July 2020
13th Floor Slab WIP
June 2020
11th floor slab complete
May 2020
10th floor slab complete.
April 2020
10th Floor Slab – at completion
March 2020
9th Floor Slab at completion
February 2020
Work started for 8th Floor Slab
January 2020
4th Floor Slab Complete