December 2021
2nd aluform in progress
October 2021
Plinth completed
September 2021
First slab work in progress
July 2021
First slab work in progress
June 2021
Shear Wall till First Slab Completed, Backfilling Work in Progress
May 2021
Foundation Completed, Basement slab work in progress
March 2021
Foundation Works in Progress