December 2020
1St Podium Floor Slab work is in progress
November 2020
1st Podium Floor Slab Work in progress.
October 2020
Back filling work/Plinth PCC work is in progress.
September 2020
Backfilling Work/Plinth PCC Work is in progress
August 2020
Plinth beam & Backfilling work is in progress.
July 2020
Pile Cap & Plinth beam work is in progress.
June 2020
Pile Cap & Plinth beam work is in progress
May 2020
Pile Cap Work is in progress.
April 2020
Pile Cap Work is in progress
March 2020
Pile Cap Work is in progress.
February 2020
Pile Cap Work is in progress
January 2020
Pilling work in Progress.