August 2023
External paint in progress
July 2023
External paint in progress
June 2023
External paint in progress
May 2023
External paint in progress
April 2023
Flooring Completion and External paint in progress
March 2023
Flooring Completion
February 2023
Terrace Slab Completed.
January 2023
20th Floor Slab work is in progress.