Terrace slab & Blockwork completed, 14th floor Gypsum work in progress, 14th floor Waterproofing in progress & 7th floor tiling in progress.
July 2023
Terrace slab completed, 16th floor Blockwork in progress, 14th floor Gypsum work in progress, 9th floor Waterproofing in progress & 3rd floor tiling in progress.
June 2023
21st floor slab in progress, 15th floor Blockwork in progress, 13th floor Gypsum work in progress, 8th floor Waterproofing in progress & 1st floor tiling in progress.
May 2023
20th slab in progress, 15th floor Blockwork in progress, 10th floor Gypsum work in progress & 7th floor Waterproofing in progress.
April 2023
19th slab WIP. Blockwork- up to 14th floor completed, Gypsum- 9th floor WIP, waterproofing 6th floor completed.
March 2023
17th slab WIP. Blockwork- up to 13th floor completed, Gypsum- 8th floor completed, waterproofing 5th floor completed.
February 2023
16th slab WIP. Blockwork- up to 10th floor completed, Gypsum- 6th floor completed, waterproofing 4th floor completed.
January 2023
15th slab WIP. Blockwork- up to 7th floor completed, Gypsum- 5th floor completed, waterproofing 2nd floor completed.