17th floor slab completed. 18th floor slab in progress, 12th floor Blockwork in progress, 4th floor Gypsum work in progress, 2nd floor Waterproofing in progress.
September 2023
15th floor slab completed. 16th floor slab in progress, 8th floor Blockwork in progress.
August 2023
13th floor slab completed. 14th floor slab in progress, 6th floor Blockwork in progress.
July 2023
10th floor slab completed. 11th floor slab in progress.
June 2023
9th floor slab completed. 10th floor slab in progress.
May 2023
8th slab in progress.
April 2023
Mivan 6th floor slab WIP.
March 2023
Mivan 4th floor slab completed.
February 2023
2nd slab completed. Mivan 1st slab setting out wip.
January 2023
2nd slab completed. Mivan 1st slab setting out wip.