Terrace slab completed, 15th floor Blockwork in progress, 7th floor Gypsum work in progress, 8th floor Waterproofing in progress & 1st floor tiling in progress.
April 2023
21st floor slab WIP, 11th & 12th floor blockwork wip, gypsum-6th floor wip., waterproofing- up to 5th floor completed.
March 2023
18th-floor slab WIP, 9th & 10th-floor blockwork WIP, gypsum-4th floor WIP, waterproofing- up to 3rd floor completed.
February 2023
16th floor slab WIP, 7th & 8th floor blockwork wip, gypsum-3rd floor wip, waterproofing- up to 1st floor completed.