Terrace slab & Blockwork completed, 20th floor Gypsum work in progress, 19th floor Waterproofing in progress & 15th floor tiling in progress.
September 2023
Terrace slab & Blockwork completed, 16th floor Gypsum work in progress, 18th floor Waterproofing in progress & 10th floor tiling in progress.
August 2023
Terrace slab & Blockwork completed, 14th floor Gypsum work in progress, 15th floor Waterproofing in progress & 4th floor tiling in progress.
July 2023
Terrace slab & Blockwork completed, 13th floor Gypsum work in progress, 14th floor Waterproofing in progress & 3rd floor tiling in progress.
June 2023
Terrace slab completed, 15th floor Blockwork in progress, 9th floor Gypsum work in progress, 12th floor Waterproofing in progress & 3rd floor tiling in progress.
May 2023
Terrace slab completed, 15th floor Blockwork in progress, 7th floor Gypsum work in progress, 8th floor Waterproofing in progress & 1st floor tiling in progress.
April 2023
21st floor slab WIP, 11th & 12th floor blockwork wip, gypsum-6th floor wip., waterproofing- up to 5th floor completed.
March 2023
18th-floor slab WIP, 9th & 10th-floor blockwork WIP, gypsum-4th floor WIP, waterproofing- up to 3rd floor completed.
February 2023
16th floor slab WIP, 7th & 8th floor blockwork wip, gypsum-3rd floor wip, waterproofing- up to 1st floor completed.